O\'BAHN TUNNEL

DETAILS

Construction of new underground bus tunnel into the Adelaide CBD

OWNERSA State Government
CONTRACTORSMcCONNELL DOWELL, Rayners Building Supplies (SA)
LOCATIONAdelaide, SA
SCOPE
  • * Hyperseal BR
  • * Hyperseal DP-2010
  • * Hyperseal D-230 Joiners
  • * Hyperseal Xseal 600

SYDNEY INTERNATIONAL AIRPORT CARPARK

DETAILSConstruction of new Northern Carpark Number 1
OWNERNSW State Government/Macquarie Bank
CONTRACTORSABIGROUP
LOCATIONMascot, Sydney, NSW Australia
SCOPE
  • * KIM concrete admixture was used at the terminal staff carpark
  • * Movement joints were used in this area.
  • * Membranes were applied to the Level 8 section movement joints.
  • * Centre Bulb was applied to this area.

RANDWICK RACECOURSE

DETAILS

Re-development of existing grandstand and construction of new grandstand buildings

OWNERNSW State Government
CONTRACTORSBROOKFIELD MULTIPLEX
LOCATIONRandwick, Sydney, NSW Australia
SCOPE
  • * KIM admixture product was used for the tunnels used by the horses and Baricote was used to repair the tie-bolt holes.
  • * Hyperseal BR, a waterstop joint product, was also used

ENERGY AUSTRALIA TRAINING CENTRE

DETAILSConstruction of new training centre
OWNEREnergy Australia
CONTRACTORSMULTIPLEX
LOCATIONSilverwater, Sydney, NSW, Australia
SCOPE
  • * KIM admixture

SYDNEY FISH MARKETS EXTENSION

DETAILS

Extension to building

OWNERCatchers Trust and the Sydney Fish Market Tenants and Merchants Pty Ltd
CONTRACTORSBUILDCORP
LOCATIONPyrmont, Sydney, NSW Australia
SCOPE
  • * Hyperseal D200, PVC waterstop, was used for concrete construction of basement stairwell.

WEST RYDE COMMUNITY CENTRE

DETAILSConstruction of new community centre
OWNERRyde City Council
CONTRACTORSBUILTFORM CONSTRUCTIONS
LOCATIONWest Ryde, Sydney, NSW, Australia
SCOPE

Liquid membranes applied to internal and external wet areas

SYDNEY CRICKET GROUND (SCG)

DETAILSConstruction of new stadium grandstand building & carpark
OWNERNSW State Government/SCG Trust
CONTRACTORSAW EDWARDS
LOCATIONRandwick, Sydney, NSW Australia
SCOPE
  • * Sheet membranes were used on the sheet pile walls & concrete binding slab to the ramp of a new tunnel.

SYDNEY DESALINATION PLANT & PUMP STATION

DETAILSConstruction of water desalination plant
OWNERSydney Water
CONTRACTORSWATER DELIVERY ALLIANCE: BOVIS LEND LEASE, Mc CONNELL DOWELL, KBR
LOCATIONKurnell, Sydney, NSW, Australia
SCOPE
  • * Krystol Internal Membrane (concrete supplied by Boral).
  • * Hyperseal & Fuko Waterstop treatments.
  • * Pump out station, substation and below-grade areas.

WAVERLEY PAVILION

DETAILS

Re-development of sports pavilion with function rooms and tiered spectator seating.

OWNERWaverley Council
CONTRACTORSNATIONAL BUILDPLAN
LOCATIONWaverley Sydney, NSW, Australia
SCOPE
  • * KIM waterproofing admixture
  • * Waterstop joint treatments
  • * Liquid membrane was applied to the lower and upper level floors as well as the roof level. We also filled and repaired form holes.

KINGSFORD SUBSTATION

DETAILS

Construction of new major zone substation

OWNEREnergy Australia
CONTRACTORSDE MARTIN & GASPARINI PTY LTD
CONSULTANTS

Hyder Consulting - Structual Engineers

LOCATIONBunnerong Rd, Kingsford Sydney, NSW, Australia
SCOPE
  • * KIM was used in the lower cable pits, connecting cable pits and base slabs, below ground walls, transformer pits,
    and oil containment pits.